Difference between revisions of "PITMinutes 03-27-2017"

From CASA Wiki
Jump to: navigation, search
(Agenda and Notes)
(Agenda and Notes)
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
 
== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, K. Baggett, A. Freyberger, R. Geng, C. Hovater, A. Hutton, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, R. Nelson, T. Plawski, and T. Reilly
+
R. Bachimanchi, K. Baggett, E. Daly, A. Freyberger, C. Hovater, A. Hutton, G. Krafft, A. Kimber, R. Legg, M. McC. F. Marhauser, R. Nelson, T. Powers, T. Plawski, T. Reilly, R. Rimmer, and S. Suhring
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 31: Line 31:
 
Radiation shielding at end of C100s has been explored by Legg.
 
Radiation shielding at end of C100s has been explored by Legg.
 
preliminary design has been completed. goal to help save girders.
 
preliminary design has been completed. goal to help save girders.
 +
 +
New module will be C57. More planning for the 2018 Module needed.
 +
 
4. Regular reporting; Josh, Tom, and Thomas in two weeks.
 
4. Regular reporting; Josh, Tom, and Thomas in two weeks.
  

Latest revision as of 14:22, 27 March 2017

Attendance

R. Bachimanchi, K. Baggett, E. Daly, A. Freyberger, C. Hovater, A. Hutton, G. Krafft, A. Kimber, R. Legg, M. McC. F. Marhauser, R. Nelson, T. Powers, T. Plawski, T. Reilly, R. Rimmer, and S. Suhring

Agenda and Notes

1. Operations Status and Summary

Recovery Plans. Still Diagnosing Cryo problems. Week or so to open cold compressor up. Getting old CC4 back in a couple weeks. If compressors not viable, will reconfigure. Only 4 K work over the summer. Probably no 2 K ops until late summer.


2. Backing Pump Discussion

Additional data mining performed. Consult with Benesch and . Gigi marcy looked at geome34try and suggested ,. Capacitor pumps on order anyway. Go through and sellect a promising module for test. 4 weeks plan will be presented. Next Steps


3. Gradient Team (Baggett)

Gradient Team Status Report


Radiation shielding at end of C100s has been explored by Legg. preliminary design has been completed. goal to help save girders.

New module will be C57. More planning for the 2018 Module needed.

4. Regular reporting; Josh, Tom, and Thomas in two weeks.

Girder Particulate Summary

Action Items