1. Operations Status and Summary

Recovery Plans. Still Diagnosing Cryo problems. Week or so to open cold compressor up. Getting old CC4 back in a couple weeks. If compressors not viable, will reconfigure. Only 4 K work over the summer. Probably no 2 K ops until late summer.


2. Backing Pump Discussion

Additional data mining performed. Consult with Benesch and . Gigi marcy looked at geome34try and suggested ,. Capacitor pumps on order anyway. Go through and sellect a promising module for test. 4 weeks plan will be presented. Next Steps


3. Gradient Team (Baggett)

Gradient Team Status Report


Radiation shielding at end of C100s has been explored by Legg. preliminary design has been completed. goal to help save girders.

New module will be C57. More planning for the 2018 Module needed.

4. Regular reporting; Josh, Tom, and Thomas in two weeks.

Girder Particulate Summary