1. Operations Status and Summary
 
1. Operations Status and Summary
  
He Processing complete! Mike Drury will report 1 month from now.
+
Mike Drury will report in two weeks on He processing from now.
 +
C. Reece/R. Geng will report in two weeks on cavity contaminates.
  
 
Arne reports that preliminary assessment of Mike's data means that we should be able to run the C20s low enough that trip rates will be good.
 
Arne reports that preliminary assessment of Mike's data means that we should be able to run the C20s low enough that trip rates will be good.
Line 13: Line 14:
 
RF soak status? Begun in the north. Cryo problems in the south. Ops drive highs have been increased to allow large trip rates so that the trip data for the newly He processes cavities may be acquired quickly. Slight SNAFU reported during the meeting. Radiation trips were stimulated by some of the high gradient running during the meeting.
 
RF soak status? Begun in the north. Cryo problems in the south. Ops drive highs have been increased to allow large trip rates so that the trip data for the newly He processes cavities may be acquired quickly. Slight SNAFU reported during the meeting. Radiation trips were stimulated by some of the high gradient running during the meeting.
  
2. Investigation team for heat and He pressure in R100 (Daly, Mounts)
+
2. 10 Hz Noise in Linac (Davis)
  
Already follow-up from two weeks ago. L. King reports pressure transducers available now at either end of linacs and near "T"s in the middle of linac at He flow split. Presently for monitoring only. Maybe eventually could be used for active feedback.
+
3. 1L22 Investigations/Findings/Cure (Mounts/Suhring/Bachimachi)
  
3. C75 Project Summary Documentation (Krafft, Freyberger)
+
4. Q0/Heaters Work Around (Freyberger)
 +
 
 +
5. Options for Obtaining Energy Margin (Powers)
 +
 
 +
6. Module up to air investigation
 +
 
 +
7. C75 Project Summary Documentation (Krafft, Freyberger)
  
 
     Requirements Discussion
 
     Requirements Discussion
Line 28: Line 35:
 
     C75 Charge Document  
 
     C75 Charge Document  
  
4. CEBAF Beamline Vacuum (Geng)
+
8. CEBAF Beamline Vacuum (Geng)
  
 
     CEBAF Beamline Vacuum
 
     CEBAF Beamline Vacuum

Revision as of 10:59, 23 November 2015

PITMinutes 11-23-2015 [edit] Attendance

R. Bachimanchi, S. Cooper, M. Drury, E. Daly, A. Freyberger, R. Geng, C. Hovater, L. King, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, H. Wang, H. Zhang [edit] Agenda and Notes

1. Operations Status and Summary

Mike Drury will report in two weeks on He processing from now. C. Reece/R. Geng will report in two weeks on cavity contaminates.

Arne reports that preliminary assessment of Mike's data means that we should be able to run the C20s low enough that trip rates will be good.

RF soak status? Begun in the north. Cryo problems in the south. Ops drive highs have been increased to allow large trip rates so that the trip data for the newly He processes cavities may be acquired quickly. Slight SNAFU reported during the meeting. Radiation trips were stimulated by some of the high gradient running during the meeting.

2. 10 Hz Noise in Linac (Davis)

3. 1L22 Investigations/Findings/Cure (Mounts/Suhring/Bachimachi)

4. Q0/Heaters Work Around (Freyberger)

5. Options for Obtaining Energy Margin (Powers)

6. Module up to air investigation

7. C75 Project Summary Documentation (Krafft, Freyberger)

   Requirements Discussion
   First Draft version is attached below, modeled on tables in the 

Cornell ERL "Project Definition Design Report". It contains input from Rimmer, Hutton, and Krafft but needs work on the cryomodule side. Daly and Mounts to help complete. Arne to derive cooling power requirement for charter document. Arne suggested publishing in tech note in about 6 weeks. Krafft will shepherd.

   C75 Project Requirements
   Gradient Maintenance Document
   C75 Charge Document 

8. CEBAF Beamline Vacuum (Geng)

   CEBAF Beamline Vacuum
   Field Emission Mitigation Project Charter 

[edit] Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)

Heat For Project Charter (freyberger)