Difference between revisions of "PITMinutes 12-14-2020"

From CASA Wiki
Jump to: navigation, search
(Agenda and Notes)
(Agenda and Notes)
 
Line 13: Line 13:
 
[https://casa.jlab.org/LINACPIT/Dec_14_202_Long_Range_LINAC_PIT_issues.pptx Challenges Working on Aging Equipment]
 
[https://casa.jlab.org/LINACPIT/Dec_14_202_Long_Range_LINAC_PIT_issues.pptx Challenges Working on Aging Equipment]
  
Action Item
+
3. Next Meeting early next year: Noise abatement and ground loops
  
New Ion pump evaluation;
+
Action Item

Latest revision as of 14:13, 14 December 2020

Attendance

K. Baggett, J. Benesch, M. Bickley, T. Carlino, G. Ciovati, J. Creel, E. Daly, K. Davis, M. Drury, C. Hovater, N. Huque, F. Humphrey, T. Ganey, C. Ginsburg, A. Kimber, L. King, G. Krafft, F. Marhauser, R. Michaud, C. Mounts, R. Nelson, W. Oren, A. Palczewski., T. Plawski, T. Powers, J. Preble, C. Reece, T. Reilly, A. Seryi, A. Solopova, M. Spata, and P. Vasilauskis

Agenda and Notes

1. Operations Status and Summary/Review (Bickley)

Scheduled down. Lots of work on NLINAC refurbishment.

2. NLINAC Refurbishment Challenges (Palczewski)

Challenges Working on Aging Equipment

3. Next Meeting early next year: Noise abatement and ground loops

Action Item