PITMinutes 05-22-2017
Attendance
R. Bachimanchi, K. Baggett, A. Freyberger, R. Geng, C. Hovater, G. Krafft, A. Kimber, C. Mounts, T. Powers, T. Plawski, T. Reilly, R. Rimmer, S. Suhring, and H. Wang.
Agenda and Notes
1. Operations Status and Summary
Twenty years plan for meeting performance and maintaining
12 GeV performance. Gradient Achievement and maintenance plans being
developed. Need 8 New C75 modules over 5 years. 37 weeks/yr goal.
Obselescence plan will also be included (old analogue to digital)
Presentation is two weeks. Potential new cold box in plan
(calling infrastructure might make funding easier)
Extensive discussion about potential radiation monitorring and how might get information about "dose to C100 failure".
2. "Staytreat"
Now August 2-3.
3. Performance of C57
Gigi's talk delayed due to new addition to his family. Presentation in two weeks.
4. Particulates reporting; SRF in Dirty Machine Workshop: HZB.
Josh, Tom, and Thomas in two weeks.
Action Items
Leadership of quenches. Offline discussion.