Attendance
K. Baggett, J. Benesch, M. Bickley, E. Daly, K. Davis, M. Drury, C. Hovater, R. Geng, C. Ginsburg, K. Jordan, A. Kimber, L. King, G. Krafft, F. Marhauser, R. Michaud, C. Mounts, R. Nelson, W. Oren, A. Palczewski., T. Plawski, T. Powers, J. Preble, T. Reilly, A. Seryi, S. Suhring, M. Spata, and H. Wang
Agenda and Notes
1. Operations Status and Summary/Review (Bickley)
New Module a good performer. It's doing about 105 MeV. Cavity two had vacuum issues solved by setting to 19.5 MeV. Best cryomodule in the machine now. Cavity Eight had a low onset of FE, running at 12.5 MeV; running now without FE.
2. Waveform Faults Waveforms (Powers)
CEBAF Vacuum: "Cold" Vacuum System and Interlocks
Linac Vacuum Section: CEBAF Design Handbook
CEBAF Vacuum System and Interlocks for Original 4 GeV Accelerator
Beam Pipe and Waveguide Vacuum Interlocks (Author: K. Jordan)
WBS1 VACUUM CONTROL SYSTEM (Author: K. Jordan)
CEBAF C100 Style Vacuum Interlocks
3. Cavity Gradient Degradation (Benesch)
4. Vacuum Trip Thresholds for Various Sites (Geng)