PITMinutes 02-15-2016
Attendance
R. Bachimanchi, S. Cooper, E. Daly, K. Davis, M. Drury, C. Hovater, R. Geng, A. Hutton, L. King, G. Krafft, F. Marhauser, C. Mounts, C. Reece, T. Reilly, R. Rimmer, T. Powers, H. Wang
Agenda and Notes
1. Operations Status and Summary
Piezo work started on R100. Should be possible to
get some microphonic damping. Stay tuned, code/software
problems.
Regular beam studies on Tuesdays and thursdays for RF recovery.
One hour machine ops devoted to Fast X-ray detection of FE, able to tune for reduced losses in . Establish baselines for future comparisons.
C100 tests (determine best pressure "defined by highest operating gradient" to operate at)
Got 70% of cavities back up to E_maxop values, but were having cooling/instability problems when operating at high values.
destinguish/study SEL GDR trip differences (Rama)
Future mechanical investigations to elliminate vibrations in the first place may be appropriate going forward.
2. Superinsulation Damage? (???)
3. R&D for improving and maintaining CEBAF gradient (in situ?)