PITMinutes 10-26-2015

From CASA Wiki
Revision as of 09:35, 26 October 2015 by Krafft (Talk | contribs) (New page: == Attendance == R. Bachimanchi, S. Cooper, A. Freyberger, R. Geng, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, J. Preble, T. Reilly, R. Rimmer, H. Wang == Age...)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Attendance

R. Bachimanchi, S. Cooper, A. Freyberger, R. Geng, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, J. Preble, T. Reilly, R. Rimmer, H. Wang

Agenda and Notes

1. Operations Status and Summary

He Processing complete! Mike D. will report 1 month from now

Implications for run?

RF soak status

2. Investigation team for heat and He pressure in R100 (Daly, Mounts)

Individual cavity heaters in R100 have been implemented and testing to see if can get better performance started.

Better instrumentation? Follow-up on making this happen?

3. C75 Project Summary Document (Krafft, Freyberger)

4. CEBAF Beamline Vacuum (Geng)

Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)