PITMinutes 02-05-2017

From CASA Wiki
Revision as of 14:36, 5 February 2018 by Krafft (Talk | contribs) (Agenda and Notes)

Jump to: navigation, search

Attendance

R. Bachimanchi, K. Baggett, J. Benesch, G. Ciovati, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, T. Plawski, C. Reece, R. Rimmer, D. Seidman, and H. Wang.

Agenda and Notes

1. Operations Status and Summary/Review (Freyberger)

Four Hall Ops has started. Beam current has been up to about

one pass (300 muA in the

both Linacs) RF not entirely stable yet, but no indication of BBU instability yet. Keeping my fingers crossed. We've had beam loss and lots of separator tuning. Haven't seen clear hot spots. 5 RF trips/hr and 5 MPS trips/hr. Fluctuating RF?

will be increasing current soon.

C75 Review will be held Thursday Feb. 15. Here is the talk repository.

Practice session will be held this Friday, Feb. 9 in this room.

2. Installation of FEL Cryomodules (Baggett)


3. Draft C75 Risk Assessment (Krafft)

Draft Risk Presentation for C75 Review

4. Draft Cryomodule Specification (Benesch)

Jay has written up a set of goals for the cryomodules: Draft Cryomodule Specification

5. Draft Acceptance Criteria (Legg)

Bob shared the LCLS II module acceptance criteria that the LCLS II project is working under. We should perhaps adopt something similar for C75? (Discuss Pros and Cons)

LCLS II Module Acceptance Criteria

Frank and Gigi (mainly) have written up a C75 performance specification document.

JLAB-TN-17-055: Draft C75 Specification Document

Action Items

Leadership of quenches. Offline discussion.

Complete C75 Module Specifications (Marhauser, Benesch, Krafft)

C100 Refurbishment Project for the future?