PITMinutes 02-05-2017
Attendance
R. Bachimanchi, K. Baggett, J. Benesch, G. Ciovati, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, T. Plawski, C. Reece, R. Rimmer, D. Seidman, and H. Wang.
Agenda and Notes
1. Operations Status and Summary/Review (Freyberger)
Beam On! Physics starting. SRF systems detected, by tripping, the 5.1 Richter earthquake centerred in Dover, DE.
2. Installation of FEL Cryomodule (Baggett)
3. Draft C75 Risk Assessment (Krafft)
Draft Risk Presentation for C75 Review
4. Draft Cryomodule Specification (Benesch)
Jay has written up a set of goals for the cryomodules: Draft Cryomodule Specification
5. Draft Acceptance Criteria (Legg)
Bob shared the LCLS II module acceptance criteria that the LCLS II project is working under. We should perhaps adopt something similar for C75? (Discuss Pros and Cons)
LCLS II Module Acceptance Criteria
Frank and Gigi (mainly) have written up a C75 performance specification document.
JLAB-TN-17-055: Draft C75 Specification Document
Action Items
Leadership of quenches. Offline discussion.
Complete C75 Module Specifications (Marhauser, Benesch, Krafft)
C100 Refurbishment Project for the future?