PITMinutes 08-17-2015

From CASA Wiki
Revision as of 09:17, 17 August 2015 by Krafft (Talk | contribs)

Jump to: navigation, search

Attendance

R. Bachimanchi, J. Benesch, A. Freyberger, R. Geng, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, T. Plawski, R. Rimmer, T. Powers, H. Wang, H. Zhang

Agenda and Notes

1. Operations Status and Summary

Cryo systems are being repaired and checked out. Additional vain bending in CHL 2 observed. Repairs started in parallel in CHL 1 repairs. Tentatively same restart in fall.

Drury thinks one module behind, Arne perhaps thinks it's more like 3. With 3 crews, maybe a week or two delay to ops. Also, looking for cavities to not He process.

New results from Cornell in Archive on surface treatments in archive. Need to digest.

S&T review. No recommendations from committee. Lots of probing on the accelerator improvement plan. Consider 2 C-100s for performance improvement instead of He process et al to get big jumps in gradient. Good argument for continuing C-75. Will need to investigate this.

SRF staff are national treasure; best on planet. They need to grow.

2. Module RF Soak Planning (R. Bachimanchi)

3. Gradient degradation: root causes and in-situ recovery techniques (Geng)

  • Useful guidance and Exercise. Please complete surveys

Action Items