PITMinutes 08-12-2019

From CASA Wiki
Revision as of 13:09, 12 August 2019 by Krafft (Talk | contribs) (Agenda and Notes)

Jump to: navigation, search

Attendance =

R. Bachimanchi, K. Baggett, G. Ciovati, H. Fanning, C. Hovater, G. Krafft, A. Kimber, K. Macha, Ju. Musson, J. Musson, T. Plawski, T. Powers, R. Rimmer, and C. Reece.

Agenda and Notes

1. Operations Status and Summary/Review (Bickley)

Physics run extended so less time for shutdown. Good reliability running at low energy. Re-planned summer maintenance work. Rebuilt C100 will go on but swap the NL07 will be put on hold. Low energy setup with reduced heating accomplished.

Plan for module swaps complete.

2. In Situ Q_L Measurements (Marhauser)

Presentation on Q_L Measurement

3. Some Comments on particulates (Geng)

Many valve closure tests completed and log entries made. Particulates ranging in size from sub-micron to several microns are observed in the tests.

Action Items

Leadership of quenches. Offline discussion.

C100 Refurbishment Project for the future?