Attendance

R. Bachimanchi, S. Cooper, E. Daly, K. Davis, A. Freyberger, A. Hutton, G. Krafft, F. Marhauser, C. Reece, T. Reilly

Agenda and Notes

1. Operations Status and Summary

Operational at 12 GeV and traded trips for repetitive down times.

Will analyze over the next few days.

Beam ops 28th January

Jan 18-28 can RF/cavities operate without beam. Turn on/off infrastructure see microphonic effect.

Daly will compose "He boiling" TP

C100 tests (determine best pressure "defined by highest operating gradient" to operate at)

destinguish/study SEL GDR trip differences (Rama)

2. Results of He Processing (Drury)

3. C75 Project Preliminary Design Review

Project Internal Review: Thursday January 21 (Morning) Responsibility for Program/Agenda?

Cavities (FM) HOM (FM) Cryomodule (ED) Hygiene Plan (GG) Rimmer/Krafft (Specifications) Prototype Data Summary (FM) RF Power (Hovater)

Committee C Reece (chair), Andrew, Cardman)

Goal: Preliminary design review


3. Particulate-Free UHV Meeting (Geng)

Schedule for February 29 Program? Rong-liu will put together an agenda beginning of next year



Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)

Heat For Project Charter (freyberger)