Line 56: Line 56:
  
  
 
* First Draft version is attached below, modeled on tables in the
 
Cornell ERL "Project Definition Design Report". It contains input from
 
Rimmer, Hutton, and Krafft but needs work on the cryomodule side. Daly
 
and Mounts to help complete. Arne to derive cooling power requirement for charter
 
document. Arne suggested publishing in tech note in about 6 weeks. Krafft
 
will shepherd.
 
 
* [http://casa.jlab.org/LINACPIT/C75_Project_Requirements.doc C75 Project Requirements]
 
* [http://casa.jlab.org/LINACPIT/C75_Project_Requirements.doc C75 Project Requirements]
 
* [http://casa.jlab.org/LINACPIT/Comments_on_Gradient_Maintenance.docx Gradient Maintenance Document]
 
* [http://casa.jlab.org/LINACPIT/Comments_on_Gradient_Maintenance.docx Gradient Maintenance Document]
 
* [http://casa.jlab.org/LINACPIT/ProjectCharter_C75.docx C75 Charge Document]
 
* [http://casa.jlab.org/LINACPIT/ProjectCharter_C75.docx C75 Charge Document]
  
4. CEBAF Beamline Vacuum (Geng)
 
 
* [http://casa.jlab.org/LINACPIT/CEBAF_Beamline_Vacuum.pptx CEBAF Beamline Vacuum]
 
* [http://casa.jlab.org/LINACPIT/Project_Charter_CEBAF_field_emission.docx Field Emission Mitigation Project Charter]
 
  
 
== Action Items ==
 
== Action Items ==

Revision as of 12:45, 4 January 2016

Attendance

R. Bachimanchi, S. Cooper, E. Daly, K. Davis, A. Freyberger, A. Hutton, G. Krafft, F. Marhauser, C. Reece, T. Reilly

Agenda and Notes

1. Operations Status and Summary

Operational at 12 GeV and traded trips for repetitive down times.

Will analyze over the next few days.

Beam ops 28th January

Jan 18-28 can RF/cavities operate without beam. Turn on/off infrastructure see microphonic effect.

Daly will compose "He boiling" TP

C100 tests (determine best pressure "defined by highest operating gradient" to operate at)

destinguish/study SEL GDR trip differences (Rama)

2. Results of He Processing (Drury)

3. C75 Project Preliminary Design Review

Project Internal Review: Thursday January 21 (Morning) Responsibility for Program/Agenda?

Cavities (FM) HOM (FM) Cryomodule (ED) Hygiene Plan (GG) Rimmer/Krafft (Specifications) Prototype Data Summary (FM) RF Power (Hovater)

Committee C Reece (chair), Andrew, Cardman)

Goal: Preliminary design review


3. Particulate-Free UHV Meeting (Geng)

Schedule for February 29 Program? Rong-liu will put together an agenda beginning of next year



Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)

Heat For Project Charter (freyberger)

Kimber and Nelson to invite list (Krafft)