Difference between revisions of "PITMinutes 10-26-2015"

From CASA Wiki
Jump to: navigation, search
(New page: == Attendance == R. Bachimanchi, S. Cooper, A. Freyberger, R. Geng, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, J. Preble, T. Reilly, R. Rimmer, H. Wang == Age...)
 
Line 16: Line 16:
 
2. Investigation team for heat and He pressure in R100 (Daly, Mounts)
 
2. Investigation team for heat and He pressure in R100 (Daly, Mounts)
  
Individual cavity heaters in R100 have been implemented
 
and testing to see if can get better performance started.
 
 
* [http://casa.jlab.org/LINACPIT/R100_Heat_Team.pptx Heat Investigation]
 
* [http://casa.jlab.org/LINACPIT/R100_Heat_Team.pptx Heat Investigation]
  

Revision as of 09:36, 26 October 2015

Attendance

R. Bachimanchi, S. Cooper, A. Freyberger, R. Geng, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, J. Preble, T. Reilly, R. Rimmer, H. Wang

Agenda and Notes

1. Operations Status and Summary

He Processing complete! Mike D. will report 1 month from now

Implications for run?

RF soak status

2. Investigation team for heat and He pressure in R100 (Daly, Mounts)

Better instrumentation? Follow-up on making this happen?

3. C75 Project Summary Document (Krafft, Freyberger)

4. CEBAF Beamline Vacuum (Geng)

Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)