Difference between revisions of "PITMinutes 07-15-2019"

From CASA Wiki
Jump to: navigation, search
(Agenda and Notes)
(Agenda and Notes)
Line 8: Line 8:
  
 
Low energy setup with reduced heating accomplished.
 
Low energy setup with reduced heating accomplished.
RF is not a limitation at this energy (SS). More intelligent
+
Though overall month for ops but not so much SRF/RF
way of doing heat control? T. Powers to address his summary
+
related. Lots of difficulties with machine reproducibility,
4 weeks from now! Interaction with cryo folks re-initiated?
+
optics, etc., although some problems with separators.
Krafft to contact Creel.
+
Seem to be moving now.
  
 
2. Data Extraction LLRF (Julia Musson)
 
2. Data Extraction LLRF (Julia Musson)
Line 35: Line 35:
 
Goal to have regular maintenance activity plan by end of year.
 
Goal to have regular maintenance activity plan by end of year.
  
3  Neutron Detectors (Degtiarenko)
+
[https://casa.jlab.org/LINACPIT/JuMussonPresentation.pptx Data Extraction Presentation]
 
+
Continued discussion on Neutron Detectors
+
  
 
== Action Items ==
 
== Action Items ==

Revision as of 13:19, 15 July 2019

Attendance

R. Bachimanchi, K. Baggett, M. Drury, P. Degtiarenko, C. Hovater, G. Krafft, A. Kimber, T. Plawski, T. Powers, R. Rimmer, C. Reece, T. Rielly, A. Seryi, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary/Review (Bickley)

Low energy setup with reduced heating accomplished. Though overall month for ops but not so much SRF/RF related. Lots of difficulties with machine reproducibility, optics, etc., although some problems with separators. Seem to be moving now.

2. Data Extraction LLRF (Julia Musson)

Data Extraction Presentation

3. Some Comments on particulates (Geng)

4. Plasma Processing (Powers)

Plasma processing project gaining traction. Kurt Macha has designed two carts needed to in situ clean. All equipment ordered, here, buil;t up by Oct. 1. Test cavity is identified and being put together. first tests in CMTF. Visited FERMI; use HOM filters to excite plasma. Use two RF sources at two frequencies to excite various modes. SNS plus mass flow measurement.

Tests  [1] Do no harm

[2] clean up dirty cavity [3] take and improve cavities from "dirty" cryomodule [4] P1 dissassembly check

Goal to have regular maintenance activity plan by end of year.

Data Extraction Presentation

Action Items

Leadership of quenches. Offline discussion.

C100 Refurbishment Project for the future?