Line 16: Line 16:
  
 
Plasma processing project gaining traction.
 
Plasma processing project gaining traction.
Orders placed for equipment reproducing SNS system.
+
Kurt Macha has designed two carts needed to in situ
Goal to have regular maintenance activity during summer next year.
+
clean. All equipment ordered, here, buil;t up by Oct. 1.
half processed every summer.
+
Test cavity is identified and being put together.
 +
first tests in CMTF. Visited FERMI; use HOM filters to excite plasma.
 +
Use two RF sources at two frequencies to excite various modes.
 +
SNS plus mass flow measurement.
 +
Tests  [1] Do no harm
 +
[2] clean up dirty cavity
 +
[3] take and improve cavities from "dirty" cryomodule
 +
 
 +
Goal to have regular maintenance activity plan by end of year.
  
 
3  Neutron Detectors (Degtiarenko)
 
3  Neutron Detectors (Degtiarenko)

Revision as of 13:53, 17 June 2019

Attendance

K. Baggett, M. Drury, P. Degtiarenko, C. Hovater, G. Krafft, A. Kimber, T. Plawski, T. Powers, R. Rimmer, C. Reece, T. Rielly, A. Seryi, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary/Review (Bickley)

Low energy setup with reduced heating accomplished. RF is not a limitation at this energy (SS). More intelligent way of doing heat control? T. Powers to address his summary 4 weeks from now! Interaction with cryo folks re-initiated? Krafft to contact Creel.

2. Plasma Processing (Powers)

Plasma processing project gaining traction. Kurt Macha has designed two carts needed to in situ clean. All equipment ordered, here, buil;t up by Oct. 1. Test cavity is identified and being put together. first tests in CMTF. Visited FERMI; use HOM filters to excite plasma. Use two RF sources at two frequencies to excite various modes. SNS plus mass flow measurement.

Tests  [1] Do no harm

[2] clean up dirty cavity [3] take and improve cavities from "dirty" cryomodule

Goal to have regular maintenance activity plan by end of year.

3 Neutron Detectors (Degtiarenko)

Continued discussion on Neutron Detectors

Neutron Detectors Updated PPT

Action Items

Leadership of quenches. Offline discussion.

C100 Refurbishment Project for the future?