Difference between revisions of "Model Team Feb 10 2015"

From CASA Wiki
Jump to: navigation, search
(New page: ==Agenda == # Preparation for Feb 13th restart ## Current decks status/CED status ## ''OTR in Hall A to be added (yves)'' ## ''BSY dump added to CED, segmentation checked''. ## Hall B mod...)
 
(Agenda)
Line 11: Line 11:
 
## Allsave/CED crosscheck tool
 
## Allsave/CED crosscheck tool
 
##: Theo Larrieu
 
##: Theo Larrieu
#Tesplans review
+
## ''Theo checked that the allsaves include everything thats in CED''
## What is left to do and prioritize it
+
##: Review testplans and close/update as needed
+
# Mid to long term model development
+
## Prepare for summer 2016 run (two halls at five pass with one recirculation)
+
##: Yves, Jay working on it.
+
## Integrate injector model with CEBAF model
+
##: Will resurrect discussions with Alicia and injector group (Yves)
+
## Dogleg focussing studies. Does it have to be included in model ?
+
## Develop procedure to crosscheck measured body gradient with machine.
+
##:  Can be an ATLIS. So far, ARC1 and ARC2 are the only ones for which we adjusted
+
##:  the body gradient from machine measurements.
+
## Feature requests for operational tools (EDT,elegant,etc..)
+
### EDT to have support for loading alternate optics via SDDS
+
### qSUtility to support zigzag scans
+
## Inclusion of multipole in model. Where is it needed ?
+
##: Recent measurements/TOSCA show that Lambertson has a big quad and skew quad component
+
## Study of effect of orbits in spreader/recombiner on
+
### First and second order dispersion terms
+
## Linac accelerating profiles loaded into model
+
### Evaluate effect on focussing and need to rematch at spreader
+
# Develop performance metrics for model improvement
+
#: '' i.e sum of squares of dispersion correction quads delta,''
+
#: ''tune time per arc, etc.. needs to be fleshed out and written down to eventually''
+
#: ''have tools to support this.''
+
---
+

Revision as of 12:21, 10 February 2015

Agenda

  1. Preparation for Feb 13th restart
    1. Current decks status/CED status
    2. OTR in Hall A to be added (yves)
    3. BSY dump added to CED, segmentation checked.
    4. Hall B model for upcoming run
      tief adding a skew quad to beamline
    5. Inclusion of 5th pass separation
      ready (Yves)
    6. Allsave/CED crosscheck tool
      Theo Larrieu
    7. Theo checked that the allsaves include everything thats in CED