1. Operations Status and Summary/Review (Freyberger)
 
1. Operations Status and Summary/Review (Freyberger)
  
Four Hall Ops has started. Beam current has been up to about 70 muA one pass (420 muA in the
+
Four Hall Ops has started. Beam current has been up to about  
North Linac) RF not entirely stable yet, but no indication of BBU instability yet. Keeping my
+
one pass (300 muA in the
fingers crossed.
+
both Linacs) RF not entirely stable yet, but no indication of BBU instability yet. Keeping my
 +
fingers crossed. We've had beam loss and lots of separator tuning. Haven't
 +
seen clear hot spots. 5 RF trips/hr and 5 MPS trips/hr. Fluctuating RF?
  
C75 Review will be held Friday Feb. 15. Here is the talk repository.
+
will be increasing current soon.
  
Practice session will be held this Friday, Feb. 8 in this room.
+
C75 Review will be held Thursday Feb. 15. Here is the talk repository.
  
2. Installation of FEL Cryomodule (Baggett)
+
Practice session will be held this Friday, Feb. 9 in this room.
 +
 
 +
2. Installation of FEL Cryomodules (Baggett)
  
  
Line 39: Line 43:
  
 
[https://casa.jlab.org/LINACPIT/2017-11-22_Draft_3.0.pdf JLAB-TN-17-055: Draft C75 Specification Document]
 
[https://casa.jlab.org/LINACPIT/2017-11-22_Draft_3.0.pdf JLAB-TN-17-055: Draft C75 Specification Document]
 
  
 
== Action Items ==
 
== Action Items ==

Revision as of 14:36, 5 February 2018

Attendance

R. Bachimanchi, K. Baggett, J. Benesch, G. Ciovati, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, T. Plawski, C. Reece, R. Rimmer, D. Seidman, and H. Wang.

Agenda and Notes

1. Operations Status and Summary/Review (Freyberger)

Four Hall Ops has started. Beam current has been up to about

one pass (300 muA in the

both Linacs) RF not entirely stable yet, but no indication of BBU instability yet. Keeping my fingers crossed. We've had beam loss and lots of separator tuning. Haven't seen clear hot spots. 5 RF trips/hr and 5 MPS trips/hr. Fluctuating RF?

will be increasing current soon.

C75 Review will be held Thursday Feb. 15. Here is the talk repository.

Practice session will be held this Friday, Feb. 9 in this room.

2. Installation of FEL Cryomodules (Baggett)


3. Draft C75 Risk Assessment (Krafft)

Draft Risk Presentation for C75 Review

4. Draft Cryomodule Specification (Benesch)

Jay has written up a set of goals for the cryomodules: Draft Cryomodule Specification

5. Draft Acceptance Criteria (Legg)

Bob shared the LCLS II module acceptance criteria that the LCLS II project is working under. We should perhaps adopt something similar for C75? (Discuss Pros and Cons)

LCLS II Module Acceptance Criteria

Frank and Gigi (mainly) have written up a C75 performance specification document.

JLAB-TN-17-055: Draft C75 Specification Document

Action Items

Leadership of quenches. Offline discussion.

Complete C75 Module Specifications (Marhauser, Benesch, Krafft)

C100 Refurbishment Project for the future?