Difference between revisions of "PITMinutes 09-26-2016"

From CASA Wiki
Jump to: navigation, search
Line 6: Line 6:
  
 
1. Operations Status and Summary
 
1. Operations Status and Summary
 
C50-12 installed. Testing tonight Commissioning and
 
checkout ???.
 
 
microphonics??? Tuner dampers tested Thursday:
 
cavities 1 6 7 8 have been damped others still show
 
fluctuations. Tested again tonight.
 
  
 
Field Emission and Radiation Measurements.
 
Field Emission and Radiation Measurements.
 
accumulation downstream. Cavity-cavity and module to module.
 
accumulation downstream. Cavity-cavity and module to module.
  
Q vs. E on the NL12. Good idea to continue!
+
C100 He processing.
 
+
C100 He processing. NL23 improvments on field emitters.  6 FE
+
cavities processed. Continuing.
+
  
 
2. Gradient Team  (Bob Legg)
 
2. Gradient Team  (Bob Legg)

Revision as of 13:30, 26 September 2016

Attendance

R. Bachimanchi, G. Ciovati, C. Hovater, G. Krafft, A. Kimber, R. Legg, C. Mounts, R. Nelson, T. Powers, T. Reilly, C. Reece, B. Rimmer

Agenda and Notes

1. Operations Status and Summary

Field Emission and Radiation Measurements. accumulation downstream. Cavity-cavity and module to module.

C100 He processing.

2. Gradient Team (Bob Legg)

First Pass at closeout document Process to close out with stakeholders Return to Pre-team

4. Field Emitters Movement (Geng/Zhang)

Indigo Site available The indico web site for the followup meeting is

LLRF FIrmware Recommendations


5. General Discussion on Future Directions (Krafft)


6. Regular Reporting

Girder Particulate Summary

Action Items