== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, G. Ciovati, A. Freyberger, C. Hovater, G. Krafft, A. Kimber, C. Mounts, R. Nelson, T. Powers, T. Reilly, C. Reece, B. Rimmer
+
R. Bachimanchi, G. Ciovati, C. Hovater, G. Krafft, A. Kimber, R. Legg, C. Mounts, R. Nelson, T. Powers, T. Reilly, C. Reece, B. Rimmer
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 22: Line 22:
 
cavities processed. Continuing.
 
cavities processed. Continuing.
  
3. C75 Mock-up Results (Gigi/Bob)
+
2. Gradient Team  (Bob Legg)
  
First look at data
+
First Pass at closeout document
 +
Process to close out with stakeholders
 +
Return to Pre-team
  
4. Follow up Field emission Workshop (Geng)
+
4. Field Emitters Movement (Geng/Zhang)
  
 
Indigo Site available
 
Indigo Site available
 
The indico web site for the followup meeting is
 
The indico web site for the followup meeting is
  
https://www.jlab.org/indico/event/173/
+
[https://casa.jlab.org/LINACPIT/LLRF_Firmware_Recs_Status_8_29_16.pptx LLRF FIrmware Recommendations]
  
Rongli
 
  
  
5. LLRF Firmware Recs Summary (Rama)
+
5. General Discussion on Future Directions (Krafft)
 +
 
  
[https://casa.jlab.org/LINACPIT/LLRF_Firmware_Recs_Status_8_29_16.pptx LLRF FIrmware Recommendations]
 
  
 
6. Regular Reporting
 
6. Regular Reporting

Revision as of 13:28, 26 September 2016

Attendance

R. Bachimanchi, G. Ciovati, C. Hovater, G. Krafft, A. Kimber, R. Legg, C. Mounts, R. Nelson, T. Powers, T. Reilly, C. Reece, B. Rimmer

Agenda and Notes

1. Operations Status and Summary

C50-12 installed. Testing tonight Commissioning and checkout ???.

microphonics??? Tuner dampers tested Thursday: cavities 1 6 7 8 have been damped others still show fluctuations. Tested again tonight.

Field Emission and Radiation Measurements. accumulation downstream. Cavity-cavity and module to module.

Q vs. E on the NL12. Good idea to continue!

C100 He processing. NL23 improvments on field emitters. 6 FE cavities processed. Continuing.

2. Gradient Team (Bob Legg)

First Pass at closeout document Process to close out with stakeholders Return to Pre-team

4. Field Emitters Movement (Geng/Zhang)

Indigo Site available The indico web site for the followup meeting is

LLRF FIrmware Recommendations


5. General Discussion on Future Directions (Krafft)


6. Regular Reporting

Girder Particulate Summary

Action Items