Line 23: Line 23:
 
2. Investigation team for heat and He pressure in R100 (Daly, Mounts)
 
2. Investigation team for heat and He pressure in R100 (Daly, Mounts)
  
 +
Already follow-up from last week.
 
L. King reports pressure transducers available now at either end of linacs
 
L. King reports pressure transducers available now at either end of linacs
 
and near "T"s in the middle of linac at He flow split.
 
and near "T"s in the middle of linac at He flow split.
 
Presntly for monitorring only. Maybe eventually could be used for
 
Presntly for monitorring only. Maybe eventually could be used for
 
active feedback.
 
active feedback.
 
Follow-up on making this happen?
 
  
 
3. C75 Project Summary Documentation (Krafft, Freyberger)
 
3. C75 Project Summary Documentation (Krafft, Freyberger)

Revision as of 08:54, 27 October 2015

Attendance

R. Bachimanchi, S. Cooper, M. Drury, E. Daly, A. Freyberger, R. Geng, C. Hovater, L. King, G. Krafft, F. Marhauser, C. Mounts, T. Powers, T. Plawski, H. Wang, H. Zhang

Agenda and Notes

1. Operations Status and Summary

He Processing complete! Mike Drury will report 1 month from now.

Arne reports that preliminary assessment of Mike's data means that we should be able to run the C20s low enough that trip rates will be good.

RF soak status? Begun in the north. Cryo problems in the south. Ops drive highs have been increased to allow large trip rates so that the trip data for the newly He processes cavities may be acquired quickly. Slight SNAFU reported during the meeting. Radiation trips were stimulated by some of the high gradient running during the meeting.

2. Investigation team for heat and He pressure in R100 (Daly, Mounts)

Already follow-up from last week. L. King reports pressure transducers available now at either end of linacs and near "T"s in the middle of linac at He flow split. Presntly for monitorring only. Maybe eventually could be used for active feedback.

3. C75 Project Summary Documentation (Krafft, Freyberger)

  • Requirements Discussion
  • First Draft version is attached below. It has contains input from

Rimmer, Hutton, and Krafft but needs work on the cryomodule side. Daly and Mounts to help complete. Arne to derive power requirement for charter document.

4. CEBAF Beamline Vacuum (Geng)

Action Items

Complete Project Charter Document; Project Leader (Freyberg, Rimmer, Krafft, Hutton)

Data mining for field emission (Geng)

C75 parameter table! (krafft, rimmer, marhauser)

Heat For Project Charter (freyberger)