Difference between revisions of "PITMinutes 10-22-2018"

From CASA Wiki
Jump to: navigation, search
(Agenda and Notes)
(Agenda and Notes)
Line 25: Line 25:
 
[https://casa.jlab.org/LINACPIT/C100_System_improvement_Discussions_18JUNE2018.pptx Tony's C100 Refurbishment Brainstorming ppt]
 
[https://casa.jlab.org/LINACPIT/C100_System_improvement_Discussions_18JUNE2018.pptx Tony's C100 Refurbishment Brainstorming ppt]
  
3. Plasma Cleaning (Powers)
+
3. RATN (Attenuator Adjustments) (Powers)
  
[https://casa.jlab.org/LINACPIT/C100status_8-30-18.pptx Plasma Cleaning Notes]
+
Attenuators on several systems were adjusted so that
 +
upper limit of klystron operational range still in rising
 +
portion of the gain curve. Hope is to mitigate out-of-lock
 +
events. Summary report attached.  
  
 +
[https://casa.jlab.org/LINACPIT/RATN_exercise_16Oct2018.docx Attenuator Adjustment Tests]
  
4. Beam Pulsing for JLEIC (Guo)
+
4. Plasma Cleaning (Powers)
  
[https://casa.jlab.org/LINACPIT/CEBAF_pulsed_beam_study_08212018.pptx Beam Pulsing Measurements at CEBAF]
+
Funding of Option one from previous discussion of plasma cleaning will
 +
likely be funded. Here is the report repeated.
 +
 
 +
[https://casa.jlab.org/LINACPIT/Plasma_processing_for_RF_PIT_8Oct18.pptx Plasma Cleaning Notes]
  
 
== Action Items ==
 
== Action Items ==

Revision as of 08:37, 24 October 2018

Attendance

R. Bachimanchi, K. Baggett, C. Hovater, G. Krafft, A. Kimber, C. Mounts, R. Nelson, T. Plawski, T. Powers, C. Reece, R. Rimmer, A. Solopova. S. Suhring, and A. Seryi.

Agenda and Notes

1. Operations Status and Summary/Review (Freyberger)

Rough sledding the past few weeks, but aperture now clear.

OPS funding requests being gathered by Bickley. Please coordinate with him old and new funding requests for FY2019.

Physics is now getting substantial "available" hours.

2. LLRF Plans and Heater Tests (Hovater)

C100 System Improvement Discussion

Items Request Email

C100 Refurbishment Brainstorming List

Tony's C100 Refurbishment Brainstorming ppt

3. RATN (Attenuator Adjustments) (Powers)

Attenuators on several systems were adjusted so that upper limit of klystron operational range still in rising portion of the gain curve. Hope is to mitigate out-of-lock events. Summary report attached.

Attenuator Adjustment Tests

4. Plasma Cleaning (Powers)

Funding of Option one from previous discussion of plasma cleaning will likely be funded. Here is the report repeated.

Plasma Cleaning Notes

Action Items

Leadership of quenches. Offline discussion.

C100 Refurbishment Project for the future?