2. CEBAF Accelerator Module Status (Drury)
 
2. CEBAF Accelerator Module Status (Drury)
  
[https://casa.jlab.org/LINACPIT/Oct_2017_Testing_Summary.pptx Accelerator Advisory Committee Presentation]
+
[https://casa.jlab.org/LINACPIT/Oct_2017_Testing_Summary.pptx NL13 and C100 Performance: Oct 2017 Tests]
  
 
3. SRF R&D Plan Beginnings (Reilly)
 
3. SRF R&D Plan Beginnings (Reilly)

Revision as of 15:45, 6 November 2017

Attendance

R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Plawski, T. Reilly, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary (Freyberger)

Steady cleanup and module filling progress. About to go from one plant to two CHL plants. Two plant OPS all up on Friday. Beam setup after Thanksgiving.

2. CEBAF Accelerator Module Status (Drury)

NL13 and C100 Performance: Oct 2017 Tests

3. SRF R&D Plan Beginnings (Reilly)

Accelerator Advisory Committee Presentation

4. C75 Performance Specifications and Plan (Krafft, Freyberger)

C75 Draft Specifications

Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)


Action Items

Leadership of quenches. Offline discussion.