Difference between revisions of "PITMinutes 11-06-2017"

From CASA Wiki
Jump to: navigation, search
Line 1: Line 1:
 
== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Powers, T. Plawski, C. Reece, R. Rimmer, T. Reilly, and S. Suhring.
+
R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Plawski, T. Reilly, and S. Suhring.
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 7: Line 7:
 
1. Operations Status and Summary (Freyberger)
 
1. Operations Status and Summary (Freyberger)
  
Steady cleanup and module filling progress. Next week for 2 K
+
Steady cleanup and module filling progress. About to go from
 +
one plant to two pl;ants. Two plant OPS all up on Friday.
 +
NLINAC. Beam setup after thanksgiving.Next week for 2 K
 
on one plant. 2 K on both plants around the 4th of Nov.
 
on one plant. 2 K on both plants around the 4th of Nov.
 
Lots of work has been done and lots remains to recover.
 
Lots of work has been done and lots remains to recover.

Revision as of 15:37, 6 November 2017

Attendance

R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Plawski, T. Reilly, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary (Freyberger)

Steady cleanup and module filling progress. About to go from one plant to two pl;ants. Two plant OPS all up on Friday. NLINAC. Beam setup after thanksgiving.Next week for 2 K on one plant. 2 K on both plants around the 4th of Nov. Lots of work has been done and lots remains to recover. Oct. 1 starts in a few weeks.

2. CEBAF Accelerator Module Status (Drury)

3. SRF R&D Plan Beginnings (Reilly)

Accelerator Advisory Committee Presentation

4. C75 Performance Specifications and Plan (Krafft, Freyberger)

C75 Draft Specifications

Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)


Action Items

Leadership of quenches. Offline discussion.