1. Operations Status and Summary  
 
1. Operations Status and Summary  
 
OPS Staytreat
 
Focus on reliability
 
 
Stonger SRF Compenent Again discussion
 
 
Klystron spares gone. Switches to power starved cavities
 
accomplished. Between 2 and 5 MeV energy gain.
 
 
Vacuum spikes to reliablility (Talk@Staytreat)
 
 
Changing machine: stabilization (Bialas and/or Powers)
 
  
  

Revision as of 13:14, 23 May 2016

Attendance

R. Bachimanchi, S. Cooper, K. Davis, M. Drury, A. Freyberger, C. Hovater, G. Krafft, F. Marhauser, C. Mounts, R. Nelson, T. Plawski, C. Reece, T. Reilly, S. Suhring

Agenda and Notes

1. Operations Status and Summary


2. FE/Particulate Meeting Report (Geng)

Follow on activity and future planning


3. Capture degradation rate?

Look at archiver data and compare?

Other ideas?