== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, K. Baggett, J. Benesch, G. Ciovati, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, T. Plawski, C. Reece, R. Rimmer, D. Seidman, and H. Wang.
+
R. Bachimanchi, K. Baggett, J. Benesch, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, R. Nelson, T. Plawski, R. Rimmer, and H. Wang.
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 7: Line 7:
 
1. Operations Status and Summary/Review (Freyberger)
 
1. Operations Status and Summary/Review (Freyberger)
  
Four Hall Ops has started. Beam current has been up to about 70 muA one pass (420 muA in the
+
Four Hall Ops has started. Beam current has been up to about  
North Linac) RF not entirely stable yet, but no indication of BBU instability yet. Keeping my
+
300 muA total in both linacs. RF not entirely stable yet, but
 +
no indication of BBU instability yet. Keeping my
 
fingers crossed.
 
fingers crossed.
  
C75 Review will be held Friday Feb. 15. Here is the talk repository.
+
We've had beam loss and lots of separator tuning. Haven't
 +
seen clear hot spots. 5 RF trips/hr and 5 MPS trips/hr. Fluctuating RF?
  
Practice session will be held this Friday, Feb. 8 in this room.
+
Because no hot spots observed, will be increasing current soon.
  
2. Installation of FEL Cryomodule (Baggett)
+
C75 Project and Implementation Review will be held Thursday, Feb. 15. Here is the talk repository.
  
 +
[https://www.jlab.org/indico/event/251/ Site for C75 Project and Implementation Review Talks]
 +
 +
Practice session will be held this Friday, Feb. 9 in this room.
 +
 +
2. Installation of FEL Cryomodules (Baggett)
 +
 +
The F100 and SL21 cryomodules from the FEL will be moved to
 +
CEBAF. F100 will probably replace lowest-performing C100
 +
and SL21 will replace a C20. Specific choice not completed yet
 +
but there is a strong desire to have a C100 available for
 +
investigation and refurbishment.
  
 
3. Draft C75 Risk Assessment (Krafft)
 
3. Draft C75 Risk Assessment (Krafft)
  
 +
Please check for completeness of topics.
 
[https://casa.jlab.org/LINACPIT/C75_Risk_Assessment.pptx Draft Risk Presentation for C75 Review]
 
[https://casa.jlab.org/LINACPIT/C75_Risk_Assessment.pptx Draft Risk Presentation for C75 Review]
  
Line 39: Line 53:
  
 
[https://casa.jlab.org/LINACPIT/2017-11-22_Draft_3.0.pdf JLAB-TN-17-055: Draft C75 Specification Document]
 
[https://casa.jlab.org/LINACPIT/2017-11-22_Draft_3.0.pdf JLAB-TN-17-055: Draft C75 Specification Document]
 
  
 
== Action Items ==
 
== Action Items ==

Latest revision as of 15:51, 5 February 2018

Attendance

R. Bachimanchi, K. Baggett, J. Benesch, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, R. Nelson, T. Plawski, R. Rimmer, and H. Wang.

Agenda and Notes

1. Operations Status and Summary/Review (Freyberger)

Four Hall Ops has started. Beam current has been up to about 300 muA total in both linacs. RF not entirely stable yet, but no indication of BBU instability yet. Keeping my fingers crossed.

We've had beam loss and lots of separator tuning. Haven't seen clear hot spots. 5 RF trips/hr and 5 MPS trips/hr. Fluctuating RF?

Because no hot spots observed, will be increasing current soon.

C75 Project and Implementation Review will be held Thursday, Feb. 15. Here is the talk repository.

Site for C75 Project and Implementation Review Talks

Practice session will be held this Friday, Feb. 9 in this room.

2. Installation of FEL Cryomodules (Baggett)

The F100 and SL21 cryomodules from the FEL will be moved to CEBAF. F100 will probably replace lowest-performing C100 and SL21 will replace a C20. Specific choice not completed yet but there is a strong desire to have a C100 available for investigation and refurbishment.

3. Draft C75 Risk Assessment (Krafft)

Please check for completeness of topics. Draft Risk Presentation for C75 Review

4. Draft Cryomodule Specification (Benesch)

Jay has written up a set of goals for the cryomodules: Draft Cryomodule Specification

5. Draft Acceptance Criteria (Legg)

Bob shared the LCLS II module acceptance criteria that the LCLS II project is working under. We should perhaps adopt something similar for C75? (Discuss Pros and Cons)

LCLS II Module Acceptance Criteria

Frank and Gigi (mainly) have written up a C75 performance specification document.

JLAB-TN-17-055: Draft C75 Specification Document

Action Items

Leadership of quenches. Offline discussion.

Complete C75 Module Specifications (Marhauser, Benesch, Krafft)

C100 Refurbishment Project for the future?