Difference between revisions of "PITMinutes 11-20-2017"

From CASA Wiki
Jump to: navigation, search
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Plawski, C. Reece, T. Reilly, and S. Suhring.
+
R. Bachimanchi, K. Baggett, G. Ciovati, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, C. Mounts, T. Plawski, C. Reece, and H. Wang.
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 21: Line 21:
 
F. Marhauser has made a start. When document blessed, we'll send
 
F. Marhauser has made a start. When document blessed, we'll send
 
it around. Table from Arne's AAC talk.
 
it around. Table from Arne's AAC talk.
 +
 +
Spec Signoff Monday Morning after Thanksgiving.
 +
Spoke posted here
 +
Requirement 70 MeV with beam for 1 module 460 muA.
 +
19.07 @ 8e9 Q-0
 +
  
 
[https://casa.jlab.org/LINACPIT/C75_table.pptx C75 Draft Specifications]
 
[https://casa.jlab.org/LINACPIT/C75_table.pptx C75 Draft Specifications]
 +
 +
[https://casa.jlab.org/LINACPIT/2017-11-22_Draft_2.0.pdf JLAB-TN-17-055: Draft C75 Specification Document]
  
 
Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)
 
Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)
  
 +
Review: proposed date for Review
 +
Jan 11, 2018
 +
Target audience: Will, AD,
 +
Hutton Chair: Phillip, Bickley, and Geng members.
 +
 +
New Cu coated waveguide?
 +
 +
In out years is bottleneck having enough end groups?
 +
 +
 +
Rec approved for getting cavity material proc started.
  
  
Line 33: Line 52:
  
 
Complete C75 Module Specifications (Marhauser, Krafft)
 
Complete C75 Module Specifications (Marhauser, Krafft)
 +
 +
C100 Refurbishment Project for the future?

Latest revision as of 11:16, 27 November 2017

Attendance

R. Bachimanchi, K. Baggett, G. Ciovati, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, C. Mounts, T. Plawski, C. Reece, and H. Wang.

Agenda and Notes

1. Operations Status and Summary (Freyberger)

Both CHLs up. All modules full! Hot checkout for the physics run in process. Beam setup after Thanksgiving.

2. Lead Collar Update (Legg)

Recent Tests with Lead Collars

3. C75 Performance Specifications and Plan (Krafft, Freyberger)

Freyberger updated on the status of the performance plan (approved!) Need to have some agreed upon specs for project. F. Marhauser has made a start. When document blessed, we'll send it around. Table from Arne's AAC talk.

Spec Signoff Monday Morning after Thanksgiving. Spoke posted here Requirement 70 MeV with beam for 1 module 460 muA. 19.07 @ 8e9 Q-0


C75 Draft Specifications

JLAB-TN-17-055: Draft C75 Specification Document

Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)

Review: proposed date for Review Jan 11, 2018 Target audience: Will, AD, Hutton Chair: Phillip, Bickley, and Geng members.

New Cu coated waveguide?

In out years is bottleneck having enough end groups?


Rec approved for getting cavity material proc started.


Action Items

Leadership of quenches. Offline discussion.

Complete C75 Module Specifications (Marhauser, Krafft)

C100 Refurbishment Project for the future?