Steady cleanup and module filling progress. About to go from
 
Steady cleanup and module filling progress. About to go from
one plant to two pl;ants. Two plant OPS all up on Friday.
+
one plant to two CHL plants. Two plant OPS all up on Friday.
NLINAC. Beam setup after thanksgiving.Next week for 2 K
+
Beam setup after Thanksgiving.
on one plant. 2 K on both plants around the 4th of Nov.
+
Lots of work has been done and lots remains to recover.
+
Oct. 1 starts in a few weeks.
+
  
 
2. CEBAF Accelerator Module Status (Drury)
 
2. CEBAF Accelerator Module Status (Drury)
 +
 +
[https://casa.jlab.org/LINACPIT/Oct_2017_Testing_Summary.pptx NL13 and C100 Performance: Oct 2017 Tests]
  
 
3. SRF R&D Plan Beginnings (Reilly)
 
3. SRF R&D Plan Beginnings (Reilly)
Line 21: Line 20:
  
 
4. C75 Performance Specifications and Plan (Krafft, Freyberger)
 
4. C75 Performance Specifications and Plan (Krafft, Freyberger)
 +
 +
Freyberger updated on the status of the performance plan (approved!)
 +
Need to have some agreed upon specs for project.
 +
F. Marhauser has made a start. When document blessed, we'll send
 +
it around. Table from Arne's AAC talk.
  
 
[https://casa.jlab.org/LINACPIT/C75_table.pptx C75 Draft Specifications]
 
[https://casa.jlab.org/LINACPIT/C75_table.pptx C75 Draft Specifications]
Line 31: Line 35:
  
 
Leadership of quenches. Offline discussion.
 
Leadership of quenches. Offline discussion.
 +
 +
Complete C75 Module Specifications (Marhauser, Krafft)

Latest revision as of 15:51, 6 November 2017

Attendance

R. Bachimanchi, K. Baggett, M. Drury, C. Hovater, A. Freyberger, R. Geng, G. Krafft, A. Kimber, R. Legg, F. Marhauser, M. McCaughan, C. Mounts, R. Nelson, T. Plawski, T. Reilly, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary (Freyberger)

Steady cleanup and module filling progress. About to go from one plant to two CHL plants. Two plant OPS all up on Friday. Beam setup after Thanksgiving.

2. CEBAF Accelerator Module Status (Drury)

NL13 and C100 Performance: Oct 2017 Tests

3. SRF R&D Plan Beginnings (Reilly)

Accelerator Advisory Committee Presentation

4. C75 Performance Specifications and Plan (Krafft, Freyberger)

Freyberger updated on the status of the performance plan (approved!) Need to have some agreed upon specs for project. F. Marhauser has made a start. When document blessed, we'll send it around. Table from Arne's AAC talk.

C75 Draft Specifications

Discussed whether to have an internal review. Committee (Kimber, Geng, Bickley, volunteers)


Action Items

Leadership of quenches. Offline discussion.