1. Operations Status and Summary
 
1. Operations Status and Summary
  
High efficiency physics running started.
+
Physics running stabilized again. There is not much gradient margin available, especially in the NLINAC. Trip rate OK, but LEM indicates 5/hr, actually observing 8 or 9/hr.
  
News on RF separator.
 
 
Separator beginning of year.
 
 
Instabilities in 2L23. Cavities lowered to make
 
stable. Lost 2 MV cavity.
 
  
 
2. SRF Hot and Cold Topics (Reece)
 
2. SRF Hot and Cold Topics (Reece)
Line 28: Line 22:
 
[https://casa.jlab.org/LINACPIT/CEBAF_Fall2016_eReach.pdf Arne's Energy Reach Summary Document]
 
[https://casa.jlab.org/LINACPIT/CEBAF_Fall2016_eReach.pdf Arne's Energy Reach Summary Document]
  
4. Microphonic Studies
+
Problems in the newly installed cryomodule. Stimulated tuner discussion. Bad matching between
 +
drive and stepper motors. Meeting Friday scheduled to try to get closure.
 +
 
 +
 
 +
4. C57 (Reilly and Marhauser)
 +
 
 +
Two cavities meet the spec and will be put in new cryomodule.
 +
Series 001 and 003 look OK, 14.5 MV.
 +
Specs in Pansophy.
 +
Current plan C57 goes into weakest slot, probably in NLINAC.
 +
Qext came out a little off but tuned to nominal 2-3 e7.
  
Discussion whether to have regular project and
+
Make sure the two "57" cavities have the best klystrons possible.
agenda item on this subject
+
  
two cavities meet the spec.
 
will be put in new cryomodule.
 
001 and 003 look OK
 
14.5 MV
 
specs in Pansophy.
 
current plan c57 in NL12
 
q ext came tuned to 2-3 e7
 
make sure have the best klystrons we have.
 
Goes into weakest slot, probably in NLINAc.
 
  
  

Latest revision as of 15:40, 30 January 2017

Attendance

R. Bachimanchi, K. Baggett, A. Freyberger, R. Geng, C. Hovater, A. Hutton, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, R. Nelson, T. Plawski, and T. Reilly

Agenda and Notes

1. Operations Status and Summary

Physics running stabilized again. There is not much gradient margin available, especially in the NLINAC. Trip rate OK, but LEM indicates 5/hr, actually observing 8 or 9/hr.


2. SRF Hot and Cold Topics (Reece)

Feb. 6 Same "Bat-Time", Same "Bat-location"


3. Tactical PIT (Ken Baggett)

Status Presentation

Arne's Energy Reach Summary Document

Problems in the newly installed cryomodule. Stimulated tuner discussion. Bad matching between drive and stepper motors. Meeting Friday scheduled to try to get closure.


4. C57 (Reilly and Marhauser)

Two cavities meet the spec and will be put in new cryomodule. Series 001 and 003 look OK, 14.5 MV. Specs in Pansophy. Current plan C57 goes into weakest slot, probably in NLINAC. Qext came out a little off but tuned to nominal 2-3 e7.

Make sure the two "57" cavities have the best klystrons possible.


5. Regular reporting; Josh, Tom, and Thomas in two weeks.

Girder Particulate Summary

Action Items