Difference between revisions of "PITMinutes 09-26-2016"

From CASA Wiki
Jump to: navigation, search
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
== Attendance ==
 
== Attendance ==
  
G. Krafft, A. Kimber, R. Legg, F. Marhauser, T. Reilly, C. Reece, H. Zhang
+
G. Krafft, A. Kimber, R. Legg, F. Marhauser, R. Geng, C. Reece, H. Zhang
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 7: Line 7:
 
1. Operations Status and Summary
 
1. Operations Status and Summary
  
Field Emission and Radiation Measurements.
+
Field emission and radiation measurements continue.
  
 
C100 He processing.
 
C100 He processing.
Line 13: Line 13:
 
2. Gradient Team  (Bob Legg)
 
2. Gradient Team  (Bob Legg)
  
First Pass at closeout document
+
First Pass at closeout document.
Process to close out with stakeholders
+
Return to Pre-team
+
  
3. Field Emitters Movement (Geng/Zhang)
+
Process to close out with stakeholders started
  
Indigo Site available
+
Effort coordination returns to PIT (return to pre-team situation)
The indico web site for the followup meeting is
+
  
[https://casa.jlab.org/LINACPIT/LLRF_Firmware_Recs_Status_8_29_16.pptx LLRF FIrmware Recommendations]
+
[https://casa.jlab.org/LINACPIT/PIT_CloseOut_Talk.pptx Gradient Team Draft Closeout]
  
 +
3. Field Emitters Movement (Geng/Zhang)
  
 +
Meeting with Spata, He Zhang, Krafft, Geng, Roblin,
 +
and Freyberger scheduled for initial go-through on
 +
Field Emitter movement, and modelling. First meeting
 +
after this one.
  
4. General Discussion on Future Directions (Krafft)
+
4. General Discussion on Future Directions/Focus (Krafft)
 
+
 
+
  
5. Regular Reporting
+
5. Regular reporting; perhaps Josh in two weeks.
  
 
[https://casa.jlab.org/LINACPIT/Girder_Particulate_Summary2016-08-15b.pptx Girder Particulate Summary]
 
[https://casa.jlab.org/LINACPIT/Girder_Particulate_Summary2016-08-15b.pptx Girder Particulate Summary]
  
 
== Action Items ==
 
== Action Items ==

Latest revision as of 07:35, 28 September 2016

Attendance

G. Krafft, A. Kimber, R. Legg, F. Marhauser, R. Geng, C. Reece, H. Zhang

Agenda and Notes

1. Operations Status and Summary

Field emission and radiation measurements continue.

C100 He processing.

2. Gradient Team (Bob Legg)

First Pass at closeout document.

Process to close out with stakeholders started

Effort coordination returns to PIT (return to pre-team situation)

Gradient Team Draft Closeout

3. Field Emitters Movement (Geng/Zhang)

Meeting with Spata, He Zhang, Krafft, Geng, Roblin, and Freyberger scheduled for initial go-through on Field Emitter movement, and modelling. First meeting after this one.

4. General Discussion on Future Directions/Focus (Krafft)

5. Regular reporting; perhaps Josh in two weeks.

Girder Particulate Summary

Action Items