Difference between revisions of "PITMinutes 06-17-2019"

From CASA Wiki
Jump to: navigation, search
Line 1: Line 1:
 
== Attendance ==
 
== Attendance ==
  
K. Baggett, M. Bickley, P. Degtiarenko, R. Geng, C. Hovater, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, R. Nelson, and T. Powers, R. Rimmer, C. Reece, and S. Suhring.
+
K. Baggett, M. Drury, P. Degtiarenko, C. Hovater, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, R. Nelson, T. Plawski, T. Powers, R. Rimmer, C. Reece, A. Seryi, and S. Suhring.
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 8: Line 8:
  
 
Low energy setup with reduced heating accomplished.
 
Low energy setup with reduced heating accomplished.
 +
RF is not a limitation at this energy (SS). More intelligent
 +
way of doing heat control? T. Powers to address his summary
 +
4 weeks from now! Interaction with cryo folks re-initiated?
  
 
2. Plasma Processing (Powers)
 
2. Plasma Processing (Powers)

Revision as of 13:34, 17 June 2019

Attendance

K. Baggett, M. Drury, P. Degtiarenko, C. Hovater, G. Krafft, A. Kimber, F. Marhauser, C. Mounts, R. Nelson, T. Plawski, T. Powers, R. Rimmer, C. Reece, A. Seryi, and S. Suhring.

Agenda and Notes

1. Operations Status and Summary/Review (Bickley)

Low energy setup with reduced heating accomplished. RF is not a limitation at this energy (SS). More intelligent way of doing heat control? T. Powers to address his summary 4 weeks from now! Interaction with cryo folks re-initiated?

2. Plasma Processing (Powers)

Plasma processing project gaining traction. Orders placed for equipment reproducing SNS system. Goal to have regular maintenance activity during summer next year. half processed every summer.

3 Neutron Detectors (Degtiarenko)

Continued discussion on Neutron Detectors

Neutron Detectors Updated PPT

Action Items

Leadership of quenches. Offline discussion.

C100 Refurbishment Project for the future?