== Attendance ==
 
== Attendance ==
  
R. Bachimanchi, K. Baggett, M. Drury, A. Freyberger, R. Geng, C. Hovater, G. Krafft, A. Kimber, R. Legg, C. Mounts, F. Marhauser, R. Nelson, T. Plawski, T. Powers, C. Reece, T. Reilly
+
R. Bachimanchi, K. Baggett, K. Davis, M. Drury, C. Hovater, G. Krafft, R. Legg, C. Mounts, T. Plawski, T. Powers, R. Rimmer, C. Reece
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 7: Line 7:
 
1. Operations Status and Summary
 
1. Operations Status and Summary
  
Physics Beam Ops in the 12 GeV era begins!
+
Separation Commissioning was successfully
 +
completed. Optics improvement verified.
 +
 
 +
Separator Problems: Vacuum Leak in 750 MHz systems.
 +
Activated!
 +
 
 +
Beam Strike? Further investigation.
 +
 
 +
Reinstall shortly before or after holiday down.
 +
 
 +
BPM problems in separator regions?
  
Raising trip levels OK? Drury says OK for dealing with new field emitters.
 
  
 
2. Piezo Tuner Studies  (T. Pawski)
 
2. Piezo Tuner Studies  (T. Pawski)
Line 25: Line 34:
 
4. Microphonic Studies (Tom Powers)
 
4. Microphonic Studies (Tom Powers)
  
[https://casa.jlab.org/LINACPIT/RF_PIT_21_Nov.docx Tuner Measurements and Plan]
+
[https://casa.jlab.org/LINACPIT/RF_PIT_21_Nov.pptx Tuner Measurements and Plan]
  
 
Discussion whether to have regular project and
 
Discussion whether to have regular project and

Latest revision as of 10:19, 5 December 2016

Attendance

R. Bachimanchi, K. Baggett, K. Davis, M. Drury, C. Hovater, G. Krafft, R. Legg, C. Mounts, T. Plawski, T. Powers, R. Rimmer, C. Reece

Agenda and Notes

1. Operations Status and Summary

Separation Commissioning was successfully completed. Optics improvement verified.

Separator Problems: Vacuum Leak in 750 MHz systems. Activated!

Beam Strike? Further investigation.

Reinstall shortly before or after holiday down.

BPM problems in separator regions?


2. Piezo Tuner Studies (T. Pawski)

Piezo Status Report

3. C100 Investigation (Ken Baggett)

C100 Energy Reach Request

Arne's Energy Reach Summary Document

Gradient Team Extended Charter

4. Microphonic Studies (Tom Powers)

Tuner Measurements and Plan

Discussion whether to have regular project and agenda item on this subject.

5. Fast X-ray Detection (Geng)

6. Regular reporting; Josh, Tom, and Thomas in two weeks.

Girder Particulate Summary